Pilbara Implementation Team

Client: Rio Tinto Iron Ore (RTIO) Cape Lambert

Project: Reclaimer 2C Drag Chain Review and Interconnection Box project

Status: Complete

Scope:

LogiCamms was selected by Rio Tinto Iron Ore to complete the reclaimer 2C drag chain rewire and interconnection box project for RTIO Cape Lambert. LogiCamms’ Pilbara implementation team worked on site throughout the whole project delivering the supply, electrical design and fit-out, bracket fabrication and installation of four drag chain interconnection boxes. The site works ran day and night with work crews consisting of 8 and 6 man teams. Over 2,200 man hours were expelled during the shutdown works.